From 2008, UK coal- and oil-fired power stations have been governed by the Large Combustion Plant Directive. This set new limits on the amounts of Sulphur Dioxide (SOx), Nitrous Oxides (NOx) and dust power stations can emit.

  • Step 1
    Power stations had to choose whether to be part of LCPD or to request a limited life derogation (opt out).

    Power stations which opted-out are allowed to run for 20,000 hours, or until 2015, whichever comes sooner.
  • Step 2
    Those power stations which are part of LCPD had to choose to be governed in one of two ways:
    – Emission Limit Value (ELV)
    The power station must meet specific limits to the amounts of pollutants produced on a “milligramme per cubic metre of waste gas“ basis.*)
    – National Emission Reduction Plan (NERP)
    A company is given an overall allowance (= bubble: amount of a pollutant that can be emitted per year) of emissions it may produce.*) The emission allowances issued under NERP are tradable within a member state.
  • Step 3
    In addition to the above, power plants must reduce Nitrous Oxide emissions from 500 mg/Nm3 to 200 mg/Nm3 by January 1, 2016. This will entail fitting selective catalytic reduction (SCR) equipment.

*) Due to the Environment Agency regulatory framework, those stations which chose ELV were allocated an
annual limit of emissions (called a company B limit) and those stations that chose NERP were allocated site
specific annual emission limit values.

 

 

Installation

Operator

Fuel

Installed capacity

Number of boilers

Number of plant

Capacity opted in1)

Capacity opted out2)

FGD3) status

 

 

 

(MWe)

 

 

(MW)

(MW)

 

1)

Compliant with emission limits in LCPD.

2)

Limitation of operating hours to 20,000 between 01/01/2008 and 12/31/2015. No requirement to fit FGD.

3)

FGD: Flue gas desulphurisation.

Drax

Drax Power

Coal

3,960

6

1

3,960

0

Fitted

Eggborough

British Energy

Coal

2,000

4

1

2,000

0

2 units fitted

Cottam

EDF Energy

Coal

2,000

4

1

2,000

0

Fitted

Ferrybridge

Scottish & Southern Energy

Coal

2,000

4

2

1,000

1,000

Under construction

Fiddlers Ferry

Scottish & Southern Energy

Coal

2,000

4

1

2,000

0

Under construction

Didcot A

RWE npower

Coal

2,000

4

1

0

2,000

No FGD

Tilbury

RWE npower

Coal

1,020

4

2

0

1,020

No FGD

Kingsnorth

E.ON UK

Coal

2,000

4

1

0

2,000

No FGD

Ratcliffe

E.ON UK

Coal

2,000

4

1

2,000

0

Fitted

Ironbridge

E.ON UK

Coal

1,000

2

1

0

1,000

No FGD

Rugeley

International Power

Coal

1,000

2

1

1,000

0

Under construction

West Burton

EDF Energy

Coal

2,000

4

2

2,000

0

Fitted

Peterhead

Scottish & Southern Energy

CCGT

1,320

2

1

1,320

0

N/A

Longannet

Scottish Power

Coal

2,304

4

1

2,304

0

Under construction

Cockenzie

Scottish Power

Coal

1,152

4

2

0

1,152

No FGD

Aberthaw

RWE npower

Coal

1,500

3

1

1,500

0

Under construction

Kilroot

AES

Coal/Oil

520

2

1

520

0

Under construction

Uskmouth

Uskmouth Power

Coal

393

3

1

393

0

Fitted

Littlebrook

RWE npower

Oil

1,370

3

1

0

1,370

No FGD

Fawley

RWE npower

Oil

1,000

2

1

0

1,000

No FGD

Grain

E.ON UK

Oil

1,300

2

1

0

1,300

No FGD

Total

 

 

33,839

71

25

21,997

11,842